Project Description

Glenarm BESS Interconnection Study

Owner: Pasadena Water and Power (PWP)
Period: 2024 – Present

Overview

Overview

Kewo Engineering is providing an interconnection study, technical assessment, logical, and regulatory considerations to ensure the integration of the BESS into PWP’s power system. The interconnection study report will identify the effects on PWP’s 35kV subtransmission system and substations and contain the following sections:

  • Executive Summary
  • Study Assumptions
  • Voltage Assessment Results
  • Capacity Assessment Results
  • Reliability Assessment Results
  • Short Circuit Duty Results
  • Reactive Power Deficiency Analysis