Project Description

Pasadena Water and Power | Owner’s Engineering for Glenarm 25MW BESS Project
Owner: Pasadena Water and Power
Period: 2025 – 2026
Overview
Overview
Kewo Engineering is performing as Owner’s Engineering services to provide engineering review of the EPC Contractor’s submittals and support during construction for the Glenarm 25MW/100MWh Battery Energy Storage System (BESS) project. We provide engineering support in the following areas:
- Equipment: BESS modules, PCS, MV/LV Switchgear, Transformer, CT/VT, Metering, IED
- Electrical: SLD, Three-line Diagram, Schematics, Protection/Control Diagram, Metering/Comm, SCADA, Site Plan, Section View, Conduit, Grounding, Lighting, Cable Schedule
- CAISO metering to support RIG and Auxilliary / Ancillary metering
- Civil/Structural: Site Plan, Grading, Drainage, Foundation Plan and Details, Calculations
- Studies: Ground Grid, Short Circuit, Protection Coordination, Arc Flash
- BESS Controls and narrative
- Shop drawings and vendor submittals
- Factory Test Reports
- Site inspections at key points in the construction process to verify conformance with project requirements and construction drawings.
- Observe / support the engineering, procurement, construction and commissioning process
- Review final project and support review / creation of As-Built drawings